St Vincents Road FRP Boardwalks

DM Composites delivered the Design & Construct of an elevated FRP boardwalk for Lane Cove Council, providing a durable, low-maintenance pedestrian connection through steep and heavily vegetated terrain. The project combines lightweight FRP structural framing, micropile foundations and integrated pathway transitions to improve accessibility while minimising disturbance to the surrounding natural environment.

LOCATION

Located along St Vincents Road in Greenwich, NSW, the boardwalk forms part of a shared user path through a steep natural corridor near Bob Campbell Oval. The elevated structure follows the existing landscape, navigating rocky ground, established trees and dense vegetation to provide a safer pedestrian connection without extensive earthworks.

OUTCOME

A lightweight FRP boardwalk delivering safe pedestrian access through steep terrain while preserving the surrounding natural landscape.

CHALLENGES AND Solutions

CASE STUDY PDF

St Vincents Road FRP Boardwalks

Download the full case study covering scope, delivery approach, and outcomes.

View Full Case Study
PDF Document

The project required a complete elevated pedestrian structure to be constructed within a narrow, steep and heavily vegetated corridor. Rocky ground, established tree roots and restricted construction access demanded a carefully coordinated approach to foundations, structural framing and installation.

Steep and restricted terrain

Lightweight pultruded FRP components enabled progressive assembly within the narrow construction corridor, reducing reliance on heavy lifting equipment and extensive site preparation.

Low-impact micropile foundations

Micropiles provided discrete structural support points, minimising excavation and allowing the boardwalk to traverse steep, rocky ground without extensive concrete foundations.

Established trees and root systems

Foundation locations and structural spans were carefully coordinated around existing vegetation and sensitive root zones, helping preserve the natural character of the corridor.

Adaptable elevated structure

FRP columns, beams, joists and bracing were engineered to accommodate varying ground levels and the pathway alignment, allowing sections of the boardwalk to extend above the natural slope.

Durable pedestrian access

Slip-resistant FRP grating provides a corrosion-resistant, low-maintenance walking surface while allowing rainwater to drain through the deck and light and air to reach the ground beneath.

Pathway integration

Concrete transitions and associated civil works connected the elevated boardwalk with adjoining shared pathways, providing consistent surface levels, appropriate gradients and smooth pedestrian movement.